Construction
Masonry of brick walls is performed on 1-2 floors - readiness 50%, on 4-17 floors - 100%, parking - 8%. Work is underway on the installation of utilities in the parking lot (water supply and sewerage, heating and ventilation) - readiness 5%. The construction of monolithic reinforced concrete air support mines along the "I" axis is underway. Work on the installation of reinforced protective concrete screed at +58,600 has been completed. Work has begun on dismantling the tower crane.
The planned time of completion of construction
Construction
0%
0%
Facade
0%
0%
Landscaping
0%
0%
Networks
0%
0%